Make-up Air Unit Pre-Functional Checklist

The real make-up air unit checklist this product ships with — 8 sections, 31 checks, signed off by 3 roles.

ElectricalMechanicalTAB

First project free · contractors always free · no card

8Sections
31Checks
3Signature roles
Checklist preview
Submittal Data Received3 checks
Equipment shop drawings
IOM manuals
Performance data
General Installation8 checks
General appearance good
Casing condition good: no dents, leaks, door gaskets installed
Doors close tightly — no leaks
Maintenance access acceptable for unit and components
Boot between duct and unit tight and in good condition
Filters installed and tight fitting
Temperature sensors installed as required
Air-source heat pump package installed per approved submittal

Showing 11 of 31 checks.

Who signs

Mechanical Contractor

Signs to confirm their part of the work is complete and accurate, before the checklist is submitted for approval.

General Contractor

Signs to confirm their part of the work is complete and accurate, before the checklist is submitted for approval.

Commissioning Agent

Countersigns once the checklist is submitted. A Commissioning Agent's signature here is what moves it to Approved — enforced at the data layer, not just an interface convention.

Make it yours

Clone it first

This one's a shared global template, so it can't be edited directly — clone it into your org's own library to get your own editable copy.

Then edit anything

Add, remove, or reword any check in your copy — nothing is locked to the built-in wording.

And reorder to match your walk

Drag sections and checks in your copy into whatever order matches how your team actually walks the equipment.

Used alongside